- Home
- City Hall
- Divisions
- Municipal Services
- Engineering
- Construction Projects
Construction Projects
Find out what is happening on current construction projects:
- 2023 55 Avenue - Water & Sanitary replacement project
55 Avenue - Water & Sanitary replacement
Description | 55th Avenue was identified as an area in the City that was in need of an underground utility upgrade for water and sanitary. Since the water was determined to be an emergency, the City was forced to begin replacement in the fall of 2020. | |
Location(s) | 55 Avenue between Centennial Drive and 51 Street. | |
Start Date |
| |
Estimated Completion Date | Friday, October 06, 2023 | |
Consultant | Associated Engineering | |
Contractor | GS Construction | |
Road Closures | 55 Avenue between Centennial Drive & 51Street will be closed for the duration of construction. | |
Temporary Utility Shutdowns | Contractor will coordinate with the residents and setup temporary water supply lines to all affected residents on 55 Ave between Centennial Drive & 51 Street . | |
Other Information | So far the eastern half of the water main has been replaced and four water services and sanitary services have been replaced. Completed Sanitary main and services in eastern half portion of project in 2022.Replaced Sidewalk sections removed for installing services. Paved bottom lift of road in eastern half portion of project that was completed in 2022. The remaining work will be completed in 2023.This includes:
The remaining work anticipated for 2023 will require excavations in the yards of those homes that have not had service replacements yet. |
- 2023 Sidewalk project
Sidewalk Connectors and Sidewalk Rehabilitation
Description | Installation of New Sidewalk Connectors & Curb Ramps to connect to existing sidewalks to increase inclusive mobility and pedestrian access. Repair, remove and replace existing sidewalk sections identified in need of replacement during sidewalk inspections. |
Location(s) | New Sidewalk connectors - 56 Avenue on South side from 44 Street to Garwood drive intersection, tie in to existing sidewalk & 46 Street on West side from 54 Avenue to 52 Avenue. Curb Ramps - At various locations throughout the City. Locations to be determined. Sidewalk Rehabilitation - At various locations in the City. Repair, remove & replace sidewalk sections that are creating a tripping hazard and have been inspected and identified for repairs during sidewalk inspections. |
Start Date | Monday, July 04, 2023 |
Estimated Completion Date | Tuesday, October 31, 2023 |
Consultant | Not Applicable |
Contractor | J. Branco & Sons Concrete Services Ltd. |
Road Closures | No complete road closures required. |
Temporary Utility Shutdowns | No Utility Shutdowns. |
Other Information | There will be temporary single lane closure during construction of the new sidewalk connectors. Please follow the posted construction signs. |
- 2023 Asphalt Overlays project
Asphalt Overlays
Description | 2023 Asphalt Overlays on 40 Avenue from Reynolds Museum Access to West City limits. Work includes mill & overlay of road surface, concrete repairs of curb & gutter and concrete median, landscape restoration, and pavement markings in areas of overlay. Asphalt patching & road restoration around utility break repairs completed at various locations throughout the City will be completed as part of the Overlays program. |
Location(s) | 1. 40 Avenue from Reynolds Museum Access to West City limits. 2. Utility break repairs asphalt patching at following locations: : 4604 - 52 Avenue, 5315 - 47 Street, 4319 - 53A Street, 5407- 57 Street, 3905 - 53A Street, 5418 - 53 Avenue, 4102- 55 Street & 5305 – 48 Street. |
Start Date | Thursday, May 25, 2023 |
Estimated Completion Date | Friday, July 14, 2023 |
Consultant | McElhanney Ltd. |
Contractor | DeFord Contracting Inc. |
Road Closures | No complete road closures expected. One lane closure & one lane alternating traffic as the milling & overlay work progresses. |
Temporary Utility Shutdowns | No Utility Shutdowns. |
Other Information | Speed limit & warning signs will be posted. There will be temporary single lane closures as work progresses between different locations. Flagpersons will direct traffic around the work zone as work progresses. |
- 2023 Lane Line Marking Rehabilitation project
Lane Line Marking Rehabilitation
|