- Home
- City Hall
- Divisions
- Municipal Services
- Engineering
- Construction Projects
Construction Projects
Find out what is happening on current construction projects:
- 55 Avenue
55 Avenue
Description | 55th Avenue was identified as an area in the City that was in need of an underground utility upgrade for water and sanitary. Since the water was determined to be an emergency, the City was forced to begin replacement in the fall of 2020. |
Location(s) | 55 Avenue between Centennial Drive and 51 Street. |
Start Date | July 27, 2022 |
Estimated Completion Date | To be determined |
Consultant | Associated Engineering |
Contractor | Martushev Logging Ltd. / Streamline Construction Co. Ltd. |
Road Closures | 55 Avenue between Centennial Drive & 51Street will be closed for the duration of construction. |
Temporary Utility Shutdowns | Contractor will coordinate with the residents and setup temporary water supply lines to all affected residents on 55 Ave between Centennial Drive & 51 Street . |
Other Information | So far the eastern half of the water main has been replaced and four water services and sanitary services have been replaced. Completed Sanitary main and services in eastern half portion of project in 2022.Replaced Sidewalk sections removed for installing services. Paved bottom lift of road in eastern half portion of project that was completed in 2022. The remaining work will be completed in 2023. This includes:
The remaining work anticipated for 2023 will require excavations in the yards of those homes that have not had service replacements yet. |
- 2022 Sidewalk project
Sidewalk Connectors and Sidewalk Rehabilitation
Description | Installation of New Sidewalk Connectors & Curb Ramps to connect to existing sidewalks to increase inclusive mobility and pedestrian access on the Automile(56 Street from 37A Avenue to 50 Avenue). Repair, remove and replace existing sidewalk sections identified in need of replacement during sidewalk inspections. |
Location(s) | New Sidewalk connectors - 37A Avenue south side ( 54 Street to 56 Street), & 48 Ave & 56 Intersection (North side). Curb Ramps - on 56 Street east side at 56 St & 37A Ave/41 Ave/43 Ave/45 Ave/47 Ave/ 47A Ave & 48 Ave intersections. Sidewalk Rehabilitation - At various locations in the City. Repair, remove & replace sidewalk sections that are creating a tripping hazard and have been inspected and identified for repairs during sidewalk inspections. . |
Start Date | July 11, 2022 |
Estimated Completion Date | Completed November 09, 2022 |
Consultant | Not Applicable |
Contractor | Jo's Concrete Services Ltd. |
Road Closures | No complete road closures required. |
Temporary Utility Shutdowns | No Utility Shutdowns. |
Other Information | There will be temporary single lane closure during construction of the new sidewalk connectors. Please follow the posted construction signs. |
- 2022 Asphalt Overlays project
Asphalt Overlays
Description | 2022 Asphalt Overlays on 56 St (HWY 2A) from 36 Avenue to South City limits & on 57 St. from 47 Ave to 48 Ave. Work includes mill & overlay of road surface, concrete repairs of curb & gutter and median, and pavement markings in areas of overlay. Asphalt patching & road restoration around utility break repairs completed at various locations throughout the City will be completed as part of the Overlays program. |
Location(s) | 1. 56 St (HWY 2A) from 36 Avenue to South City limits. 2. 57 Street from 47 Avenue to 48 Avenue & on 57 Street from Tim Horton's West entrance to 50 Avenue. 3. Utility break repairs asphalt patching at following locations: 166 Garwood Drive, 5405A -47Ave, 43 Street & 53 Avenue , 5210 - 55A Street, 52Avenue & 53Street, 171 Willow Drive, 4601 - 46Avenue, 40 Avenue & 52 Street & 54 Street between 48 Avenue & 49 Avenue. |
Start Date | Estimated start date, Sept 06, 2022 |
Estimated Completion Date | Completed September 30, 2022 |
Consultant | Not Applicable |
Contractor | Central City Asphalt Ltd. |
Road Closures | No complete road closures expected. One lane closure & one lane alternating traffic as the milling & overlay work progresses. |
Temporary Utility Shutdowns | No Utility Shutdowns. |
Other Information | Speed limit & warning signs will be posted. There will be temporary single lane closures as work progresses between different locations. Flagpersons will direct traffic around the work zone as work progresses. |
- 2022 Lane Line Marking Rehabilitation project
Lane Line Marking Rehabilitation
|